On the Aegean, work that is not scoped before winter finishes during arrival week.

Most renovation problems on this coast are not construction problems. They are calendar problems. A project discussed in August, approved in January and started in March will almost always meet the season before it meets its finish.

The months that decide a renovation are October and November. Not because work starts then, but because everything that makes the work go well has to be settled then.

Scope before budget

A budget written before the scope is understood is a guess with a number on it. The first task is to define what the project actually is: what is being replaced, what is being repaired, what is being left alone, and what the house itself is asking for. That last part is where the post-season condition of the house matters. Problems found after a summer of full use — water, electrical, joinery, surfaces — should shape the scope, not appear in the middle of it.

One brief, several quotations

Contractors can only be compared when they quote against the same written brief: the same scope, the same exclusions, the same materials and the same finish standard. Without that brief, the lowest price is usually the narrowest interpretation. With it, the differences between quotations become visible, and so do the assumptions behind them.

The right vendor is not always the cheapest one

The lowest quotation is often the one that has left the most out. It becomes expensive later, one variation at a time: the drainage that was “not included”, the second coat that was “not specified”, the electrician who was “assumed to be yours”. By the end, the cheapest price has usually become an average one, delivered late.

The highest quotation is not automatically the safest either. Price is one line of a comparison, not the comparison. What matters as much is what is written as excluded, who will actually be on site and who supervises them, whether the dates are realistic for the season, how payments are tied to progress, what warranty is given and whether the firm comes back in the first year when something settles. On this coast, it also matters whether a vendor has worked with salt, humidity and long empty winters, or only with city apartments.

The right vendor is the one whose quotation matches the brief, whose exclusions are written down, whose team is named, and whose references come from houses like yours. Sometimes that is also the lowest price. It should never be the reason.

Who manages the vendors

On most private projects, the honest answer is: everyone, and therefore no one. The architect follows the design, the main contractor follows his own scope, the pool company, the electrician, the joiner and the landscaper each follow theirs, and the owner follows all of them by message from abroad. Each party is responsible for its own work. Nobody is responsible for the points where their work meets — and that is where most delays, damage and disputes begin.

A renovation needs one person who holds the whole site on the owner’s behalf. That person gives instructions through a single channel, sets the sequence between trades, attends the site regularly rather than on request, prices every change in writing before it is made, checks work before it is accepted and before it is paid, and keeps the record of what was agreed and what was done.

That role should sit on the owner’s side of the table, independent of the contractors it supervises. A coordinator chosen or paid by the main contractor can be competent and well-meaning, but cannot be independent. When the owner is not on site, independence is the whole point.

Dates written back from arrival

The programme should start from the day the house must be ready and work backwards: final cleaning, inspection and snagging, commissioning of systems, the work itself, material lead times, permits. Many coastal municipalities restrict noisy construction in the summer months, and imported materials can take longer than anyone expects. A project with no buffer in March has no buffer at all.

The house still has to winter

A residence under renovation is still a residence. Security, water, power, protection of finished surfaces and control of who enters the property continue throughout the work. The principles in The House That Winters Well apply here too, with more people on site.

A renovation that finishes in April leaves a month for the house to settle, be cleaned, be tested and be inspected properly, as described in When a House Is Ready. A renovation that finishes in May leaves none.

Standart represents owners through renovation and project work on the Turkish coast — scope, vendor selection, site coordination and reporting, on the owner’s side. Renovation & Project Representation →